Labour and Material Payment Bonds

A labour and material payment bond guarantees that the subcontractors and suppliers on a job actually get paid. It is the one construction bond written for people who did not buy it — the trades and suppliers who dealt directly with the bonded contractor. Owners require it to keep unpaid trades off their liens and off their site; contractors carry it because trades price bonded work more sharply. Stanhope Simpson places labour and material payment bonds across Atlantic Canada.

What Is a Labour and Material Payment Bond?

A labour and material payment bond is issued at contract award alongside the performance bond, and in Canada each is usually written at 50% of the contract price. The two are separate instruments with separate limits — on a $10 million contract with 50/50 bonding there is $5 million of performance security and a further $5 million available to unpaid trades, not one shared pot.

The bond guarantees that the contractor will pay for the labour and material used on the job. If it does not, a qualifying claimant can pursue the surety directly rather than waiting on the contractor or fighting over holdback.

The standard Canadian form is CCDC 222, reissued in May 2024. It is not the only form in use — federal work uses its own, some owners use their own wording, and the differences matter more on this bond than on any other. Read the actual bond, not a summary of what bonds usually say.

Subcontractors and suppliers protected by a labour and material payment bond
L&M Bond Benefits

Why Contractors Carry a Payment Bond

Sharper pricing from your trades

Subcontractors and suppliers price credit risk. Where no payment bond is in place they typically charge more to carry it — so the bond frequently pays for part of itself in the numbers you get back.

Access to bonded work

Most public construction and a large share of institutional and lender-financed private work conditions award on providing both a performance bond and a payment bond. Without a facility, that work is closed to you.

Credibility with suppliers

A surety’s willingness to bond is a third-party opinion on your finances, character and capacity — and sureties monitor a bonded contractor’s whole work programme, not just one job.

Fewer disputes to manage

Trades with a solvent route to payment are less likely to down tools, demobilise or register liens while you sort out a cash flow problem.

One facility, both bonds

The payment bond is issued as a matched pair with the performance bond by the same surety, under the same facility, and priced together.

L&M Bond Benefits

Why Owners Require a Payment Bond

Fewer liens to administer

Trades with a bond to claim on have somewhere to go other than your land and your holdback. Waive the bond and lien administration and holdback distribution become your job.

The project keeps moving

Unpaid trades stop work. A payment bond gives them a solvent alternative source of payment, which is usually what keeps them on site while a contractor problem is worked out.

Ongoing surety oversight

Prequalification is a snapshot. A surety monitors a bonded contractor’s entire work programme continuously, which surfaces trouble on other jobs before it reaches yours.

Better pricing on the tender

Where trades know a payment bond will be in place, they do not need to load their numbers for the risk of not being paid. That shows up in what the general contractor can bid.

It is not a cure-all

A bond will not fix a project that was underfunded or badly scoped from the outset, and it does not pay amounts that were never owed. It handles contractor insolvency and non-payment, which is what it is for.

The Standard Form

CCDC 222 (2024): What Changed

The standard Canadian payment bond was reissued in May 2024, its first update since 2002. The Surety Association of Canada is clear the risk profile did not change — the coverage is the same. What changed is the process, and one provision that matters a great deal to trades.

Aerial view of a construction site featuring heavy machinery and trucks, displaying industrial activity.

A prescribed claims protocol

The form now carries three schedules — a notice of claim, a surety acknowledgement and a surety’s position — with deadlines attached to each. Claimants know what to send and when to expect an answer.

The 90-day wait is gone

Under the old form a claimant could not advance a claim until 90 days after last working. That restriction has been removed, so a claim can move as soon as notice is properly given.

No duty to tell you the bond exists

The form now states expressly that neither the bond nor the trust imposes any obligation on the owner to notify a claimant that a bond exists, and the owner need not act against the surety on your behalf. This is the change trades most need to know about.

Digital service added

The list of what counts as labour and material now includes digital service alongside water, gas, power, light, heat, oil, gasoline and telephone — a sensible modernisation for how sites actually run.

Rental equipment addressed head-on

Rental equipment directly applicable to the contract is covered. Where rent is applied toward a purchase price, recovery is capped at the prevailing industrial rental value for the period of actual use — more generous than the federal form, which excludes rent-to-own outright.

A shared pool, spelled out

The bond amount is reduced by every payment made under it, and where claims look likely to exceed it the surety can apply to the court for direction in the interest of all claimants. Being slow is expensive even inside the deadline.

The Surety Association of Canada publishes free specimen copies of the 2024 forms, and the documents are issued by the Canadian Construction Documents Committee. If the bond on your job is a single page, it is the superseded version — and the deadlines in it are different.

For Trades and Suppliers

Who Can Claim — and Who Cannot

This is where most payment bond claims are lost before they start. The standard Canadian form covers one tier of the contractual chain, and no further.

Covered: a direct contract

Subcontractors, suppliers, equipment rental firms and labour suppliers who contracted directly with the bonded contractor. If your agreement is with the general contractor named on the bond, you are a claimant.

Not covered: the second tier

A sub-subcontractor, a supplier to a subcontractor, a supplier to a supplier. Under the standard form these parties are not claimants at all — and the trap is that they hear “the project is bonded” and reasonably assume they are protected.

Federal work reaches further

The federal payment bond form extends to anyone with a direct contract with the principal or any subcontractor of the principal. On federal jobs a second-tier trade may well be covered where it would not be under the standard form.

The form on your job decides

Owners use their own wordings, provinces use their own forms, and Ontario’s public form reaches the second tier as well. Never assume the standard form applies — read the bond that is actually on your project.

Nobody has to tell you it exists

The current form expressly removes any duty on the owner to notify claimants that a bond exists, and the owner is not obliged to chase the surety for you. Silence is evidence of nothing. The 120-day clock runs whether you knew or not.

So ask, in writing, early

Request a copy from the general contractor and the owner before you mobilise. In Nova Scotia the Builders’ Lien Act lets a lien claimant demand a copy of any labour and material payment bond in writing, and it must be produced within 21 days, with a costs sanction for refusal.

The cheapest permanent fix is a clause in your own subcontract requiring the contractor to deliver a copy of any bond on execution. It costs nothing to ask for at the negotiating stage, and it removes the problem entirely.

For Claimants

How to Make a Claim, and the Clock You Are On

Timely notice is a condition precedent. Miss it and there is no claim, however good the debt. These are the deadlines on the current standard form — note the deliberate mix of calendar days on your side and business days on the surety’s.

120 days — for holdback

Notice must be given within 120 calendar days of the date you should have been paid in full under your contract with the bonded contractor.

120 days — for everything else

Notice must be given within 120 calendar days of the date you last performed labour or supplied material. That is a second, separate clock on the same debt, and it usually runs out first.

Serve all three parties

The notice goes to the surety, with copies to the contractor and the owner, in substantially the form the bond prescribes. An email to a project manager saying you have not been paid is not a notice of claim.

3 business days — acknowledgement

The surety must acknowledge your notice and tell you what documents it needs. Return them fast: its decision deadline runs from when it gets them.

10 or 25 business days — the position

The surety must state its position no later than ten business days after receiving the information it asked for, and in any event no later than twenty-five business days after your notice. Respond promptly and you can compress that to as few as thirteen.

One year — to sue

Suit must be commenced within one year of the date the contractor last performed work on the contract, including warranty work. Read that trigger carefully: it turns on an event on someone else’s contract, not on your last day.

What to send. The executed subcontract or purchase order, all change orders, invoices and progress billings, a statement of account, proof of payments received, and the outstanding amount including HST. Add a statutory declaration on payment of your own trades, a copy of any lien filed, a current workers’ compensation clearance, and a copy of the bond. The document claimants most often lack is proof of their final date of supply — delivery slips, signed tickets, timesheets. That is what substantiates the 120-day clock, so keep it.

Owed money on a job you think is bonded?

Talk to us before the clock runs. We will tell you whether a bond exists, whether you are a claimant under it, and exactly what to send — and if you are placing bonds rather than claiming on them, we do that too.

Two Routes

Bond Claim or Builders’ Lien?

An unpaid trade in Atlantic Canada usually has two routes, and they are independent of each other. You can run both — you just cannot recover twice.

What each one actually gets you

A bond claim is a cash claim against a solvent surety, up to the bond amount. A lien is a charge on land, or on holdback, which only becomes money through a court process or a settlement. One depends on the surety’s solvency; the other on the owner and the equity in the property.

Speed and cost

The bond process is built for speed: acknowledgement in three business days, a formal position inside ten to twenty-five, undisputed amounts paid ten business days after that. Starting it costs a letter and a document package. A lien means registration, then an action, then litigation.

Who each route is open to

Lien legislation runs down the contractual chain, so a sub-subcontractor or a supplier to a subcontractor still has lien rights. The standard payment bond does not reach them. For second-tier trades the lien is often the only route.

Public land changes everything

On Crown and much public work a lien cannot attach to the land, and the claim collapses into a fight over holdback. A payment bond does not care who owns the land. On public projects the bond is frequently the primary remedy rather than the backup.

Protect the lien first

Lien deadlines are almost always the shorter ones — in Nova Scotia a lien must be registered within 60 days, against 120 calendar days for the bond notice. Register first, then serve the bond notice. Losing the lien while you wait on a surety is an avoidable mistake.

Get advice on a live file

Lien deadlines are unforgiving, fact-specific, and interact with substantial performance certification and holdback release. Nothing on this page is a substitute for a construction lawyer once money is actually at stake — and the rules differ across the four Atlantic provinces.

The Rest of the Programme

Bonds That Sit Alongside a Payment Bond

A payment bond is rarely issued on its own. These are the instruments most often arranged with it, or used to deal with what happens when payment goes wrong.

Construction team reviewing project drawings on site — contractor insurance for builders and developers

The matching bond issued at award, protecting the owner rather than the trades. Separate instrument, separate limit, different trigger entirely.

The bond that comes first. That page also covers what a surety underwrites, the documents you will need, and how single-job and aggregate limits are set.

Used to discharge a registered lien from title so a project or a sale can proceed, with the bond standing in place of the land as security.

Releases statutory holdback back into a contractor’s cash flow while still protecting the owner’s position.

Covers defects in workmanship or materials during the warranty period once the work is complete.

The surety’s pre-award letter confirming the performance and payment bonds will be available if the contract is awarded.

Frequently Asked Questions About Labour and Material Payment Bonds

Under the standard Canadian form, only parties with a direct contract with the bonded contractor — its subcontractors, its suppliers, its equipment rental firms, its labour suppliers. A sub-subcontractor, or a supplier to a subcontractor, is second tier and has no claim under that form at all. Some other forms reach further: the federal payment bond extends to claimants contracting with the principal or any subcontractor of the principal, and Ontario’s public-sector form also reaches the second tier. Which form is on your job decides whether you are covered.

It is priced as a pair with the performance bond, on a rate per thousand dollars of contract value that declines as contract size rises. The two together commonly come to around one percent of the contract price, with stronger contractors rated better. Premium is adjusted on the final contract price, so increases attract additional premium and reductions can produce a refund.

A qualifying claimant serves a written notice of claim on the surety, with copies to the contractor and the owner, using the form prescribed in the bond. The surety must acknowledge within three business days and ask for the documents it needs. It then has to state its position — no later than ten business days after it receives that information, and in any event no later than twenty-five business days after the notice. Undisputed amounts are payable within ten business days of that position.

Notice must be given within 120 calendar days. For holdback, that runs from the date you should have been paid in full under your contract with the bonded contractor. For everything else, it runs from the date you last performed labour or supplied material. Those are two separate clocks on the same debt, and timely notice is a condition precedent — miss it and there is no claim, however good the debt.

Suit is a different clock again: one year from the date the contractor last performed work on the contract, including warranty work. Note that trigger carefully — it is an event on someone else’s contract, not yours.

No. It is a requirement of the owner’s procurement rather than of general law, and requirements differ by owner and province. It is standard on public construction and common on institutional, lender-financed and larger private work. Some provinces mandate it above a stated contract value for public work; the Atlantic provinces set it through tender documents and procurement policy. Read the tender.

You do not apply bond by bond. You establish a bonding facility with a surety through a broker, and once it is in place the payment bond is issued at award as a matched pair with the performance bond. Our bid bonds page sets out what a surety underwrites, what documents you will need, and how single-job and aggregate limits are set.

Ask, in writing, before you mobilise — from the general contractor and from the owner. Do not wait to be told: the current standard form expressly removes any duty on the owner to notify you that a bond exists. In Nova Scotia there is a stronger route. The Builders’ Lien Act entitles a lien claimant to demand, in writing, a copy of any labour and material payment bond posted in respect of the contract, and it must be produced within 21 days, with a costs sanction for refusal. The simplest long-term fix is a clause in your own subcontract requiring a copy of any bond to be delivered on execution.

Yes. They are independent remedies — one arises from a contract of suretyship, the other from statute — and pursuing one does not extinguish the other. You can only recover once, and a surety that pays is subrogated to your rights. The practical sequencing point is that lien deadlines are usually the shorter ones, so protect the lien first and then serve the bond notice.

Different bonds, different beneficiaries, different triggers and separate limits. The performance bond protects the owner and responds when the contractor defaults in the work. The payment bond protects trades and suppliers and responds when the contractor does not pay them. A subtrade cannot claim on a performance bond, and an owner does not use a payment bond to get the job finished.

Use the notice form prescribed in the bond and serve it on the surety with copies to the contractor and the owner. Send the executed subcontract or purchase order, all change orders, invoices and progress billings, a statement of account, proof of payments received, the outstanding amount including HST, and — the document claimants most often lack — proof of your final date of supply, such as delivery slips or signed tickets. Add a statutory declaration on payment of your own subtrades, a copy of any lien filed, a current workers’ compensation clearance, and a copy of the bond itself.

Because the surety’s deadline to state its position runs from whichever comes first: ten business days after it receives the information it asked for, or twenty-five business days after your notice. A claimant who returns the document package promptly can compress the surety’s decision from twenty-five business days to as few as thirteen. There is also a queue effect — the bond amount is reduced by every payment made under it, so on a large default the slow claimants are the ones who find the pool short.

Yes. Rental equipment directly applicable to the contract falls within the definition of material, alongside water, gas, power, light, heat, oil, gasoline and telephone or digital service. Where the rent is being applied toward a purchase price, recovery is limited to the prevailing industrial rental value of the equipment for the period it was actually used on the job, judged by prevailing rates in the local equipment market. Note that the federal form takes a different approach and excludes rent-to-own arrangements outright.

This is where the payment bond matters most. On Crown and much public work a lien cannot attach to the land itself, and the claim collapses into a fight over holdback. A payment bond is unaffected by who owns the land — it is a promise from a solvent surety, not a charge on real property. On public projects the bond is frequently the primary remedy rather than the backup.

Yes. CCDC 222 was reissued in May 2024, its first update since 2002, alongside the bid and performance bond forms. The Surety Association of Canada is clear the risk profile did not change; what changed is the process. The claims protocol now carries prescribed forms and deadlines on the surety, the old rule barring a claimant from suing until 90 days after last working has been removed, digital service was added to the covered list, and the owner’s duty to tell claimants a bond exists was expressly negated.

Yes, and it must give specific reasons in its formal position. The bond is based on the underlying contract and governed by its terms, so the surety’s liability tracks what is genuinely owed. Common grounds are late notice, the claimant being second tier and therefore not a claimant at all, amounts not properly due under the subcontract, or a dispute about the work itself. Inflating a claim tends to delay payment of the part that was good.

Frequently asked questions about labour and material payment bond claims

Not been paid?

If you think there is a bond on a job and you are out of pocket, talk to us before the clock runs. We will tell you whether you are a claimant and what to send.

Schedule a Consultation Today

Personalized insurance and surety solutions backed by decades of industry expertise. Reach out to us today and experience the Stanhope difference!